Is there a function to automatically place activities?

Modified on Fri, 26 Jan at 3:53 PM

Yes, there are.

With “Time Analysis” function in ACTY'S, based on the information held by the activities, the optimum schedule is calculated automatically to place activities. 

  • Based on the Time Now (set the current time on the computer or any date and time), time analysis is performed while considering required Duration for each Task, Constraint (relationships and restrictions between Tasks) and Calendar information, then rearrange Active Bars according to the result.



To complete the project in the shortest possible schedule, Tasks are rearranged by front-loading. 
You can also set "Start as late as possible" option for activities that you do not want to start earlier. 
You can easily adjust your schedule.



[Operation example]

Execution example of Time Analysis when project start date is delayed by 10 days

Please refer to the attached video for the operation image.






C_KTZ_FEA_4_2205_00015_00

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article