Is it possible to reflect working/non-working day information in the activity?

Modified on Thu, 11 May, 2023 at 6:56 PM

Yes, it is possible.

You can set a calendar that defines information on working days/holidays for each activity.



When performing Time Analysis or moving Bars, the duration is automatically adjusted based on the working days information in the calendar.



What is Time Analysis? 
This is a function that automatically calculates the optimum schedule based on the information held by the activities.




[Set working days/holidays in the calendar]



[Set the calendar to an activity to reflect working days/holidays]






C_KTZ_PMG_5_2205_00043_00