Yes, it is possible.
In ACTY'S, by using the standard attached tool “Roll Up Percent Complete”, the progress rate of each activity included in the Group (WBS) can be totaled to calculate the progress rate of the Group (WBS) as a whole.
You can select the numerical value used to calculate the progress rate from Duration/Quantity/Man-hours.
Even if the Group contains many activities, you can easily monitor the progress of the Group as a whole.
[Operation example]
Execution of Roll Up Percent Complete
Please refer to the attached video for the operation image.