Yes, there is.
With “Histogram” function in ACTY'S, the load status of each resource used in the project can be visually expressed.
- The assigned workload for each resource (human resources, equipment, etc.) is displayed in a stacked graph format.
- The horizontal direction of the graph represents the duration of the task and the vertical direction represents the load per time slot.
- If the total value of the pile exceeds the set Resource Availability, the excess portion is displayed in red allowing you to visually understand the overloaded state.
When you move the Bar where Resource required is set, the Histogram will also move together, so you can adjust resources while visually checking the load status.
[Example of Histogram display]
[Example of Resource Availability display]
[Operation example]
Load adjustment by using Histogram
Please refer to the attached video for the operation image.
C_KTZ_FEA_5_2205_00010_00
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article