Yes, it is possible.
By setting it with “Bar Layout” function, Total Float (spare time) can be displayed.
The Total Float value is automatically calculated according to the Time Analysis Condition Setting.
[Example: Display Total Float beside the Active Bar]
What is Total Float?
It refers to the spare time for a certain Task that can be delayed without affecting the Finish Date of the Entire Project, although it might affect the schedule of other Tasks.
What is Bar Layout?
This is a function that allows you to specify the type of Bar to be displayed in the bar chart or the property items to be displayed along with the Bar for each View.
You can freely customize the display items so that you can check the necessary information on the bar chart screen without opening the property window of the Bar.